Cheatham Lock at Cumberland River Mile 148.7 will be closed to navigation beginning at 0600 16 May 2022 and continuing through 05 August 2022 due to repairs on upper gates and culvert valves. There will be temporary openings to allow navigation passage during the listed phases posted below. During these temporary openings there will not be any restriction.

Cheatham Lock Temporary Openings

Task Name Duration Start Finish
Phase 1 14 Days 05/16/2022 05/29/2022

Lock Closed

11 Days 05/16/2022 05/26/2022
Lock Open  3 Days 05/27/2022 05/29/2022
Phase 2  14 Days 05/30/2022 06/15/2022
Lock Closed 11 Days 05/30/2022 06/09/2022
Lock Open  3 Days 06/10/2022 06/12/2022
Phase 3 14 Days 06/13/2022 06/26/2022
Lock Closed 11 Days 06/13/2022 06/23/2022
Lock Open  3 Days 06/24/2022 06/26/2022
Phase 4 14 Days 06/27/2022 07/10/2022
Lock Closed 4 Days 06/27/2022 06/30/2022
Lock Open  10 Days 07/01/2022 07/10/2022
Phase 5 14 Days 07/11/2022 07/24/2022
Lock Closed 11 Days 07/11/2022 07/21/2022
Lock Open  3 Days 07/22/2022 07/24/2022
Phase 6 11 Days 07/25/2022 08/04/2022
Lock Closed 11 Days 07/25/2022 08/04/2022

Lock Open/Project Complete

  08/05/2022  

 