  • May

    Ceremony marks completion of Center Hill Dam barrier wall

    LANCASTER, Tenn. (May 18, 2015) – Officials celebrated the completion of a barrier wall in the main dam embankment of Center Hill Dam during a ceremony today at the work platform on top of the dam. The $115 million foundation barrier wall is a key component of the U.S. Army Corps of Engineers Nashville District’s Center Hill Dam Safety Remediation Project.
  • August

    Work crews reach million-hour safety milestone at Wolf Creek Dam

    JAMESTOWN, Ky. (Aug. 17, 2012) – Construction crews at the Wolf Creek Dam Foundation Remediation Project reached a lofty safety milestone today when the men and women installing a concrete barrier wall deep into the dam’s embankment reached 550 days and one million work-hours on the job without a lost-time accident.
  • July

    Construction begins with ‘first bite’ on foundation barrier wall at Center Hill Dam

    LANCASTER, Tenn. (July 11, 2012) – The “first bite” of a $106 million drilling project to stabilize the earthen portion of the Center Hill Dam with a barrier wall was taken today by the U.S. Army Corps of Engineers Nashville District and its contractor, Bauer Foundation Corporation, as the auger of a giant drill rig turned up the first dirt to the cheers of spectators.
  • February

    Construction commotion moves Corps to Wolf Creek Dam safety milestone

    JAMESTOWN, Ky. (Feb. 24, 2012) – Wolf Creek Dam is abuzz with machinery, often bottlenecked with equipment and vehicles, and work crews move about like ants on the work platform in performance of their duties on the foundation remediation project. Despite what seems like construction commotion, there hasn’t been a lost-time accident in more than a year.