  • Update-NR 17-031: One-lane traffic set for Wolf Creek Dam bridge inspection

    JAMESTOWN, Ky. (Sept. 8, 2017) — The U.S. Army Corps of Engineers Nashville District announces that traffic crossing Wolf Creek Dam at Lake Cumberland will be subject to one-lane, one-direction control from 7 a.m. to 4:30 p.m. Sept. 19, 2017 while maintenance personnel perform a routine inspection of the bridge.
  • NR 16-013: Surface drainage correction requires lane closure on Highway 127 across Wolf Creek Dam

    Jamestown, Ky. (May 20, 2016) – During a road restoration project on Highway 127 over Wolf Creek Dam, contractors found a pocket of voids on Monday at the edge of the roadway, the result of surface drainage erosion. The Corps’ engineers have been on site since then to determine the most efficient and timely solution in order to reduce the extended lane closures currently in effect for the project.
  • NR 15-019: Nashville District highlights its notable projects leading into National Dam Safety Awareness Day

    NASHVILLE, Tenn. (May 29, 2015) – The U.S. Army Corps of Engineers Nashville District has two notable engineering projects to its credit in recent years to stop seepage through the embankments of Wolf Creek Dam in Jamestown, Ky., and Center Hill Dam in Lancaster, Tenn. In conjunction with National Dam Safety Awareness Day May 31, 2015, the district is highlighting the major effort it took to construct concrete barrier walls deep into the foundations of these dams.
  • NR 13-012: Wolf Creek Dam Ceremony location changed and security measures increased

    NASHVILLE, TENN. (April 18, 2013) – The Nashville District, U.S. Army Corps of Engineers is changing the location for the Wolf Creek Dam Completion Ceremony on Friday, April 19 due to forecasted severe weather early Friday morning that will preclude setup. The District is also increasing security measures for the ceremony.
  • NR 13-011: Public invited to Wolf Creek Dam Barrier Wall Completion Ceremony April 19

    NASHVILLE, Tenn. (April 10, 2013) – The public is invited to a barrier wall completion ceremony 10 a.m. April 19, 2013 on the work platform at Wolf Creek Dam near Jamestown, Ky., to celebrate this milestone with the U.S. Army Corps of Engineers, its contractor Treviicos-Soletanche Joint Venture, and other local, state and national officials expected at this event. Dignitaries will speak and initiate the ceremonial last concrete placement on the barrier guide wall, which signifies the official completion of the barrier wall installation.
  • NR 13-008: Corps completes barrier wall at Wolf Creek Dam

    NASHVILLE, Tenn. (March 6, 2013) – The U.S. Army Corps of Engineers Nashville District poured concrete for the last pile of the barrier wall today, which completes the last and most critical component of the dam safety project required to mitigate seepage through the karst geology deep in the foundation of Wolf Creek Dam’s embankment. It is the last of 1,197 piles that are approximately four feet in diameter and extend up to 275 feet into bedrock below the foundation of the embankment. Altogether they interlock to form the barrier wall.
  • NR 12-018: Milestone reached with completion of protective concrete embankment wall at Wolf Creek Dam

    JAMESTOWN, Ky. (June 22, 2012) – The U.S. Army Corps of Engineers Nashville District reached a major milestone here this week at the Wolf Creek Dam Foundation Remediation Project when work crews installed the 433rd and final panel in completing the protective concrete embankment wall. While this wall does not create a water barrier through the dam’s karst limestone foundation, it completes a major stage of construction that is critical to the final stage of construction – the main barrier wall, which is scheduled to be completed by December 2013.