  • NR 23-33: Kendall Recreation Area Boat Ramp set to reopen

    NASHVILLE, Tenn. (Sept. 5, 2023) – The U.S. Army Corps of Engineers Nashville District announces construction at Kendall Campground and Day Use Area, including its boat ramp and roadway along the riverside campground, is nearing completion. These areas are expected to re-open by the end of September 2023.
  • NR 23-30: Wolf Creek Dam oxygen diffuser project contract awarded

    NASHVILLE, Tenn. (Aug. 17, 2023) – The U.S. Army Corps of Engineers Nashville District announces a base contract award to Brasfield & Gorrie, L.L.C., of $16.8M for the Dissolved Oxygen facility. This is a sustainability project funded by the Section 212 Program to install an upstream diffuser system at Wolf Creek Dam on the Cumberland River in Jamestown, Kentucky.
  • NR 23-16: Reservoirs below summer pool elevations due to lack of rain

    NASHVILLE, Tenn. (June 6, 2023) – The U.S. Army Corps of Engineers Nashville District’s water managers report that two reservoirs in the Cumberland River Basin did not receive enough rain this spring to reach their traditional summer pool elevations.
  • NR 23-13: Kendall Recreation Area closure extended into August 2023

    JAMESTOWN, Ky. (May 2, 2023) – The U.S. Army Corps of Engineers Nashville District announces that Kendall Campground and Day Use Area, to include its boat ramp and roadway along the riverside campground, will remain closed into August 2023 as repairs continue to rehabilitate flood damage sustained in February 2019.
  • NR 23-03: Wolf Creek Dam oxygen diffuser project underway

    NASHVILLE, Tenn. (Feb. 9, 2023) – The U.S. Army Corps of Engineers Nashville District is executing a sustainability project funded by the Section 212 Program to install an upstream diffuser system at Wolf Creek Dam on the Cumberland River in Jamestown, Kentucky.
  • NR 22-25: Portion of Kendall Recreation Area closing for erosion control project

    JAMESTOWN, Ky. (Oct. 20, 2022) – The U.S. Army Corps of Engineers Nashville District announces that portions of Kendall Campground and Day Use Area, to include its boat ramp and roadway along the riverside campground, are closing for repairs Oct. 24, 2022, through early April 2023 to rehabilitate flood damage sustained in February 2019.
  • NR 22-22: Contract awarded for Wolf Creek Dam Spillway Gates Replacement Project

    NASHVILLE, Tenn. (Sept. 29, 2022) – The U.S. Army Corps of Engineers Nashville District awarded a $109,450,000 contract yesterday to American Bridge Company for the Wolf Creek Dam Spillway Gates Replacement Project. The project is fully funded by the Disaster Relief Supplemental Appropriations Act of 2022.
  • NR 20-030: Video highlights water management in Cumberland River Basin

    NASHVILLE, Tenn. (Dec. 10, 2020) – The public is invited to watch a newly released video that highlights how water is managed in the Cumberland River Basin in support of flood risk management, commercial navigation, hydropower production, water supply, environmental stewardship, and recreational opportunities.
  • NR 19-031: Lake Cumberland reopens recreation facilities earlier than projected

    NASHVILLE, Tenn. (May 9, 2019) -- The U.S. Army Corps of Engineers Nashville District announces recreation facilities affected by a pool of record at Lake Cumberland in February 2019 are reopening earlier than projected.
  • NR 19-016: Wolf Creek Dam decreasing releases to 43,000 cfs today

    JAMESTOWN, Ky. (March 13, 2019) – Officials with the U.S. Army Corps of Engineers Nashville District announce that releases at Wolf Creek Dam are decreasing from 52,000 cubic feet per second to 43,000 cfs by this afternoon.