    Nashville District completes Wolf Creek Dam barrier wall

    JAMESTOWN, Ky. (March 6, 2013) – Construction workers placed concrete for the last pile today, which completes the underground barrier wall and paves the way for raising the Lake Cumberland pool level. It is the last of 1,197 piles that are approximately four feet in diameter and extend 275 feet from near the top of the dam into bedrock below the foundation of the 4,000-foot long embankment of Wolf Creek Dam.
  • February

    Construction commotion moves Corps to Wolf Creek Dam safety milestone

    JAMESTOWN, Ky. (Feb. 24, 2012) – Wolf Creek Dam is abuzz with machinery, often bottlenecked with equipment and vehicles, and work crews move about like ants on the work platform in performance of their duties on the foundation remediation project. Despite what seems like construction commotion, there hasn’t been a lost-time accident in more than a year.